1.Lookingacrossthemajorityofindustries,duringwhichphaseinaprojectlifecyclearemostoftheprojectexpensesincurred? A.Conceptphase B.Developmentordesignphase C.Executionphase D.Terminationphase 对于大多数的产业,项目费用大多发生在项目生命周期中的哪一阶段? A.构思阶段 B.开发或设计阶段 C.执行阶段 D.结束阶段 2.Usingthetablebelow,thescheduleperformanceindex(SPI)forWBSElementPis: A.1.10 B.0.90 C.0.956 D.1.15 WBSElementBCWSBCWPACWP P$1,000$1,100$1,150 Q$2,000$1,800$2,100 R$1,000$1,200$1,050 S$2,000$1,900$1,800 用下表数据计算,工作分解结构WBS要素P的进度绩效指数(SPI)是: A.1.10 B.0.90 C.0.956 D.1.15 工作分解结构WBS要素计划执行预算成本BCWS已执行工作预算成本BCWP已执行工作实际成本ACWP P$1,000$1,100$1,150 Q$2,000$1,800$2,100 R$1,000$1,200$1,050 S$2,000$1,900$1,800 3.YouhaveestimatedandscheduledyourprojectbasedontheteammembersyouhavebeenassignedanddevelopedtheBCWSbaseline.However,youhavenowbeenassignednewteammemberswhoaremoreexperiencedandhighersalariedthanthoseonwhichyoubasedyourinitialestimate.Themostprobableimpactonprojectperformancewouldbe: A.NegativeCV,negativeSV B.NegativeCV,positiveSV C.PositiveCV,negativeSV D.PositiveCV,positiveSV 你对项目进行了估算和进度安排,根据团队成员情况,分配了任务并且制定了计划执行预算成本的基准.然而,分配了新的项目团队成员,他们比初始估算的成员更有经验,薪水更高.这对项目绩效最可能的影响会是: A.负的成本偏差CV,负的进度偏差SV B.负的成本偏差CV,正的进度偏差SV C.正的成本偏差CV,负的进度偏差SV D.正的成本偏差CV,正的进度偏差SV 4.Themostpreciseandaccuratetechniquefordeterminingprojectcostsisthetechnique. A.Bottom-up B.Analogy C.Budget D.Modifiedstandards 决定项目成本的最精确的和最正确的技术是什么技术 A.由下而上 B.类比 C.预算 D.修正标准 5.Thefourtypesofcostdatathatarenormallyaccumulatedandreportedaspartofacostcontrolsystemare: A.Labor,material,otherdirectcharges,managementreserve B.Labor,material,managementreserve,overhead C.Managementreserve,labor,otherdirectcharges,overhead D.Labor,material,otherdirectcharges,overhead 作为成本控制系统的一部份,要收集并且报告的四类成本数据是: A.人工,原材料,其它直接费用,管理储备 B.人工原材料,管理储备,管理费用 C.管理储备人工,其它直接费用,管理费用 D.人工原材料,其它直接费用,管理费用 6.Thetechniquescommonlyusedtodeterminetheprofitabilityofaprojectincludeallofthefollowing,except: A.Netpresentvalue(NPV)B.Internalrateofreturn(IRR) C.Paybackperiod D.Riskassessmentmodel(RAM) 通常用来计算决定项目的获利力的技术包括所有的下列项,除了: A.净现值(NPV) B.内部的回报率(IRR) C.投资回收期 D.风险评估模型(RAM) 7.Whichofthefollowingisnotconsideredadirectcostforproducingawidget? A.Thecostofthematerialsusedtoproduceawidget B.Thelaborcostsoftheworkerswhoactuallyproducedthewidget C.Therentforthebuildinginwhichthewidgetwasmanufactured D.Theequipmentusedtoproducethewidget 下列哪一项不会被考虑作为生产小器具的直接成本? A.用于生产小器具的原材料的成本 B.实际生产小器具的人工成本 C.生产制造小器具的厂房场地的租金 D.生产小器具的设备 8.Whichofthefollowingwouldnotnecessarilyincreasetheaccuracyofestimatingtheprojectcost? A.Pricingouttheworkatlowerlevelsintheworkbreakdownstructure B.Usinghistoricaldata C.Talkingtopeoplewhohaveworkedonsimilarproject D.Spendingadditionaltimeontheestimate 下列的哪一项不会必然地增加估算项目成本的准确性? A.在工作分解结构中,在较低的水平订定工作价格 B.使用历史数据 C.与有类似项目工作经验的人进行交流 D.花额外的时间进行估算 9.Whattoolmustprojectmanagersrelyupontoaccuratelyidentifythecostsassociatedwithaproject? A.Abillofmaterials B.AGanttchart C.Anarrowdiagramnetwork D.Aworkbreakdownstructure 项目经理必须依赖什么工具,以便准确识别与项目相关联的成本? A.材料单 B.甘特图 C.箭线网络图 D.工作分解结构 10.Usingthetablebelow,WBSElementQisbudgetbypercent. A.Over,16.66 B.Under,16.66 C.Over,10.0 D.Under,10.0 WBSElementBCWSBCWPACWP P$1.000$1,100$1,150 Q$2,000$1,800$2,100 R$1,000$1,200$1,050 S$2,000$1,900$1,800 利用下表数据,工作分解结构WBS要素Q是预算多少百分比 A.超过,16.66 B.低于,16.66 C.超过,10.0 D.低于,10.0 工作分解结构要素计划执行预算成本BCWS已执行工作预算成本BCWP已执行工作实际成本ACWP P$1.000$1,100$1,150 Q$2,000$1,800$2,100 R$1,000$1,200$1,050 S$2,000$1,900$1,800
信息发布:广州名易软件有限公司 http://www.myidp.net
|