11.Whichofthefollowingtypesofpaymentsonaninternationalprojectareunacceptable?
A.Offeringtopaythecountryofficialsfornotawardingtheprojecttoaparticularcompany.
B.Paymentformailservice.
C.Paymentfora“foreignworkersapplicationlicense”requiredinthecountry.
D.Paymentforpolicyprotection.
在国际项目中,下列哪种类型的付款是不可接受的?
A.为了不把项目授予一个特殊的公司,承诺向所在国官员提供的付款
B.用于邮寄服务的付款
C.用于所在国要求的“外国工人用工许可”的付款
D.用于政策保护的付款12.AbrahamMaslowdevelopedamodeltoexplainthemotivationalprocessinrelationtothewayhumanneedschangethroughoutanindividual’slifecycle,Thismodelhasfivelevels.Responsibility,asenseofaccomplishment,andasenseofcompetenceareexamplesofneedsatwhichleves?
A.Self-actualization.
B.Social.
C.Esteem.
D.Physiological.
亚伯拉罕.马斯洛提出了一个层次需求理论,解释了一个人的整个生命发展期间的不同类型的需要。责任感、成就感和能胜任的感觉属于下列哪个级别的需要?
A.自我实现
B.社会化
C.尊重
D.生理需求
13.Yourprojectteamisspendingsomuchtimereviewingpotentialchangestoaprojectthatyoudonothavetimetocompleteprojectwork.WhichofthefollowingistheLEASTlikelyreasonforthisproblem?
A.NochangecontrolboarD.B.Notenoughofanefforttodeterminewhothestakeholdersare.
C.Apoorcommunicationmanagementplan.
D.Unclearprojectcharter.
你的项目团队用大量的时间讨论一个项目的潜在变更,以至于你没有时间去完成项目。下列哪项最不可能是这个问题的原因?
A.没有变更控制委员会。
B.没有尽力去确定谁是项目干系人。
C.不完善的沟通管理计划。
D.不清楚的项目规章。
14.Formal,writtencorrespondencewiththecustomerisrequiredwhen:
A.DefectsaredetecteD.B.Acustomerrequestsadditionalworknotcoveredundercontract.
C.Theprojecthasascheduleslippagethatincludeschangestothecriticalpath.
D.Aprojecthascostoverruns.
当--------的时候,需要与客户进行正式、书面的通信。
A.发现缺陷。
B.客户要求增加合同未包括的额外工作。
C.项目有一项进度滑移,它包括对关键路径的变更。
D.一个项目成本超支。
15.Youareperformingadministrativeclosurefortheprojectexecutionphaseoftheproject.Uponcompletionofthisstep,youwillhaveprojectarchives,formalacceptance,and:
A.Projectreports.
B.LessonslearneD.C.Performancemeasurementdocumentation.
D.Statementofworkupdates.
你正在实施项目执行阶段的管理收尾工作。这一步骤完成后,你将得到项目档案、正式验收和-------------。
A.项目报告
B.教训
C.绩效测量文件
D.工作更新综述
16.Youaremanagingaprojectinajust-in-timeenvironment.Thiswillrequiremoreattention,becausetheamountofinventoryinsuchanenvironmentis:
A.45%.
B.10%.
C.12%.
D.0%.
你正在管理一个进度刚刚好的项目。这需要更多的关注,因为,在这种环境中库存量为:
A.45%
B.10%
C.12%
D.0%
17.Thesoftwaredevelopmentprojectisnotgoingwell.Thereareover30stakeholders,andnoonecanagreeontheprojectobjectives.Onestakeholderbelievestheprojectcanachievea30%improvementwhileanotherbelievesa50%improvementispossible.Theprojectmanagerthinksa10%improvementismorerealistiC.WhatistheBESTcourseofaction?
A.Moveforwardwiththeprojectandhopemoreinformationcomestolightlatertosettletheissue
B.Averagethenumbersandusethatasthegoal
C.Performafeasibilityanalysis
D.Askthesponsortomakethefinaldecision
一个软件开发项目进展不佳。这个项目有30多个干系人,他们当中没有一个人认可项目目标。一个人认为该项目可以达到30%的改进,而另一个人认为可能达到50%。项目经理则认为10%更加现实。最佳的行动路径是什么?
A.项目继续进展,希望以后获得更多的信息来解决这个问题.
B.将所有数字进行平均,把结果作为目标
C.进行一项可行性分析
D.请项目投资人做最终决定
18.Twoteammembersarehavingabigdisagreementoverthetypeofcomputerhardwaretouseontheproject.Whoshouldresolvethedispute?
A.Twomembersandtheirprojectmanager.
B.Projectmanager.
C.Management.
D.Systemsupervisor.
两名团队成员在用于项目的计算机硬件类型上有重大分歧。谁来解决这个争议?
A.这两名团队成员和他们的项目经理。
B.项目经理。
C.管理层。
D.系统总监。
19.Duetoalackofemployeetrainingandproperproductioncontrols,defectsinaproductionruncausedreworkwhichcostthecompany$500,000.Howmuchofthiscostisdirectlyattributabletotheemployeesontheproductionline:
A.$65,000
B.$25,000
C.$250,000
D.$500,000
由于缺乏员工培训和适当的生产控制,某生产操作中的缺陷造成返工,从而花费公司$500,000。这一成本中的多少是直接由于该生产线的员工造成的:
A.$65,000
B.$25,000
C.$250,000
D.$500,000
20.Duringprojectexecution,aprojectteamdeliversaprojectdeliverabletothecustomer.However,thecustomerneitheracknowledgesthedeliverablenorsaysifitisacceptable,althoughanapprovalisrequireD.WhatistheBESTthingtodo?
A.Continuewiththeproject.
B.Documentthesituation.
C.Contactmanagementforhelp.
D.Callameetingoftheteam.
在项目执行过程中,一个项目团队向客户交付一项项目可交付成果。然而,尽管需要客户的认可,但是,这个客户既没有承认也没有说是否接受这项可交付成果。最好怎样做?
A.继续进行项目。
B.把这种情况形成文件。
C.与管理层联系取得帮助。
D.召集一次团队会议。